Material Cost Variance

Learning Outcomes

  • Analyze the variance between expected material cost and actual material costs

So let’s head back to our Hupana Running Company and review their raw materials by cost and quantity to see where differences might occur, and how we calculate spending variances or quantity variances. Both are important and are used to calculate the overall spending variance.

You might want to revisit these three video tutorials before we get started here.

Material variance can vary based on material quantity, material cost or both.  Standard cost variance analysis for direct materials can be shown like this:

Spending Variance flows into Price Variance, Actual Quantity of Input at Standard Price, and Quantity Variance. Price Variance flows into Actual Quantity of Input at Actual Price. Quantity Variance flows into Standard Quantity Allowed for Actual Output at Standard Price

So we will use this chart to look at some different scenarios for Hupana Running Company.  Our original direct materials budget calls for 10,250 units of raw materials at $2 per unit to meet our manufacturing requirements. So, we budgeted to spend $21,000 on our raw materials because we wanted a little beginning inventory for the new period. What happens if the price, quantity or both change?

When we talk about expected material costs and actual material costs we need to consider a couple of factors.  First, there is the quantity of material that goes into each unit. Then there is the cost per unit of material. These two pieces of information are important to consider when analyzing the variance between expected and actual material costs.

Let’s go back to Hupana Running Company. Their direct material cost budget is as follows:

Total
Required production in pairs 2050
Units of raw material needed per pair 5
Units of raw material needed to meet production 10250
Plus desired ending raw material inventory 500
Total units of raw materials needed 10750
Less units in beginning raw material inventory 250
Units of raw materials to be purchased 10500
Cost of raw material per unit $2
Cost of raw material to be purchased $21,000

Keeping the required production in pairs at 2050, What would happen if there was a ton of waste in production and we used 7.5 units of raw material per pair, instead of 5?

Total
Required production in pairs 2050
Units of raw material needed per pair 7.5
Units of raw material needed to meet production 15375
Plus desired ending raw material inventory 500
Total units of raw materials needed 15875
Less units beginning raw material inventory 250
Units of raw materials to be purchased 15625
Cost of raw material per unit $2
Cost of raw material to be purchased $31,250

This results in a change in quantity of product, but the price remains the same. So using our chart from 10.2, we can calculate as follows:

  • Actual quantity allowed for actual output at standard price = 10,500 × $2= $21,000
  • Actual quantity of input at actual price = 15,625 × $2 = $31,250

So our spending variance is $10,250

We now have spent $31,250 on our raw materials, when we had budgeted $21,000. Waste, scrap, production issues or improper training could all have been at fault for this variance issue. This definitely needs to be reviewed.

So, what would happen if the cost per unit of input went down to $1.25, but our waste remained high?

Now we would still need to purchase 15,625 units, but at a cost of $1.25/unit so $19,531.25 would be our total spent on direct materials. Now the variances become more clear, right?

We purchased more units, but at a lower price. So we had a quantity variance and a price variance. There can be either a price variance or a quantity variance, but there can also be a combination that creates the spending variance.

Taking this information to management might be a bit uncomfortable if the first scenario happens, right? Do your homework before putting together your report. Check with your production manager and see if she can shed some light on the problem.  But, in the second scenario, the lower price per unit compensates for the additional units used!

Whichever direction this takes, you may find your production department laying blame on the purchasing team for buying substandard product. The purchasing team might blame production for sloppy work. You may need to do some sleuthing to figure this one out.

Practice Questions

Contribute!

Did you have an idea for improving this content? We’d love your input.

Improve this pageLearn More