Scheduling Tools

Learning outcomes

  • Differentiate between Gantt charts, PERT, and the critical path method

Izmailovo Hotel

As you might expect, operations managers find that complex processes involve complex planning and scheduling. Consider the Izmailovo Hotel in Moscow shown in the photograph at the right. Built to house athletes during the 1980 Olympics, the complex has 7,500 guest rooms and is one of the largest hotels in the world. Think about cleaning all those rooms—in four thirty-story-high towers—or checking in the thousands of guests. No small operation! Although the Izmailovo doesn’t produce a tangible good, it relies on many of the same operations management principles used in manufacturing to stay in business. To increase operational efficiency in complex processes like those of running a giant hotel, operations managers use three common planning tools: Gantt charts, PERT, and the critical path method (CPM).

Gantt Charts

A Gantt chart is a timeline. Multiple projects can be added to the timeline with start and finish dates, and milestones and deadlines are also reflected. This chart is used to determine how long a project will take, the resources needed, and the order in which tasks need to be completed.

Three birdhousesLet’s look at a Gantt chart for producing a birdhouse. Suppose the following activities are required to build and package each birdhouse:

  1. Determine which birdhouse the customer has ordered
  2. Trace pattern onto wood
  3. Cut the pieces of wood from the birdhouse pattern
  4. Assemble the pieces into a birdhouse
  5. Paint birdhouse
  6. Attach decorations to the birdhouse
  7. Prepare customer invoice
  8. Prepare packing and shipping label
  9. Pack birdhouse into shipping carton
  10. Deliver carton to shipping department
Gantt chart shows three main projects: Construct Birdhouse, Customer invoice, and Packing and Shipping. Construct Birdhouse has six tasks listed as part of the project. To the right of the list of projects and corresponding tasks there is a timeline showing when each task will take place. The project Construct Birdhouse starts on February 23rd with “Determine Birdhouse customer has ordered” and ends on March 6th with “Attach decorations to birdhouse”. The duration of each task is represented with a purple highlight over the days of the week that task will occur. The tasks for the project Customer Invoice and the project “Packing and Shipping” are represented in the same way. Construct Birdhouse and Customer Invoice start on February 27th while Packing and Shipping start on March 5th.

Figure 1. Gantt Chart

Below is the corresponding Gantt chart: As you can see, the tasks on the list are displayed against time. On the left of the chart are all the tasks, and along the top is the time scale. A bar represents each work task; the position and length of the bar indicate the start date, duration, and end date of the task. At a glance, we can determine the following:

  • What the various activities are
  • When each activity begins and ends
  • How long each activity lasts
  • Where activities overlap with other ones, and by how much
  • The start and end date of the whole project

Critical Path Method (CPM)

In the critical path method (CPM), the manager identifies all of the activities required to complete the project, the relationships between these activities, and the order in which they need to be completed. Then, the manager develops a diagram that uses arrows to show how the tasks are dependent on each other. The longest path through these linked activities is called the critical path. If the tasks on the critical path are not completed on time, the entire project will fall behind schedule.

To better understand how CPM works, look at Figure 2, which shows a CPM diagram for constructing a house. All of the tasks required to finish the house and an estimated time for each have been identified. The arrows indicate the links between the various steps and their required sequence. As you can see, most of the jobs to be done can’t be started until the house’s foundation and frame are completed. It will take five days to finish the foundation and another seven days to erect the house frame.

The activities linked by the solid arrows form the critical path for this project. It tells us that the fastest possible time the house can be built is 41 days, the total time needed for all of the critical path tasks. The noncritical path jobs, those connected with dashed arrows, can be delayed a bit or done early. Short delays in installing appliances or roofing won’t delay construction of the house because these activities don’t lie on the critical path.

There are eight tasks on the critical path and there are thirteen tasks total. The tasks that are not on the critical path rely on the critical path tasks to be completed. This is important because it means if a critical path task gets delayed, the whole project gets delayed. The critical path is as follows: Start flows to foundation complete flows to frame complete flows to both siding complete and cabinet and walls complete. Cabinet and walls complete flows to interior painting complete flows to carpet installation complete which flows to house ready and clean. The critical path takes a total of 38 days total. The frame must be complete before the following can happen: Electrical wiring, plumbing, and siding. Then the cabinets and walls can be completed and the roofing can be completed. After that, roofing, appliance installation, and interior painting can be completed. After that, carpet can be installed and the exterior can be completed which completes the project.

Figure 2. A CPM Network for Building a House (Attribution: Copyright Rice University, OpenStax, Modification by Lumen Learning: CC BY 4.0 license.)

PERT

Like CPM, the program evaluation and review technique (PERT) helps managers identify critical tasks and assess how delays in certain activities will affect operations or production. In both methods, managers use diagrams to see how operations and production will flow. PERT differs from CPM in one important respect. CPM assumes that the amount of time needed to finish a task is known with certainty; therefore, the CPM diagram shows only one number for the time needed to complete each activity. In contrast, PERT assigns three time estimates for each activity: an optimistic time for completion, the most probable time, and a pessimistic time. These estimates allow managers to anticipate delays and potential problems and schedule accordingly.

PRactice Question

Did you know…?

PERT was developed by the U.S. Navy. The Navy’s Special Projects Office devised this statistical technique for measuring and forecasting progress while they were designing the Polaris-Submarine weapon system and the Fleet Ballistic Missile capability.

CPM was first used for major skyscraper development in 1966 for the construction of the former World Trade Center Twin Towers in New York City.[1]